For sixty years, the critical path ran through the site. Excavation, foundations, structure, services, testing: the longest chain of work was the one the crews were doing, and project controls grew up watching it. Quantities installed, percent complete, crews on the ground, the look-ahead for next week. If the site moved, the date moved.
On a growing class of capital projects, that is no longer true. A 50 MW data centre can be built in about eighteen months and then wait years for the power to run it. A solar farm can be ready to install and wait in a queue for a grid connection. A substation can be designed, permitted and staffed and then wait for a transformer that is still a slot in a factory's order book. The finish date is set outside the fence: by a utility's queue, a manufacturer's production line and a permit office's calendar.
This post is about what that does to project controls. It walks through the evidence on the three queues outside the fence, looks at data centres as the sharpest case, explains why the usual schedule and reporting tools do not see the problem, and sets out what changes in the schedule, the contract and the team. The short version: the controls discipline of the next decade is the control of things the project does not own.
Three queues outside the fence
The evidence is clearest for three kinds of external dependency: the connection to the grid, the long-lead electrical equipment that makes the connection usable, and the permits that allow either to happen. Each has its own queue, and each queue has grown long enough to set dates.
The grid. Lawrence Berkeley National Laboratory tracks every project asking to connect to the US grid. Its 2026 edition of Queued Up counts roughly 2,061 gigawatts of capacity actively seeking interconnection at the end of 2025: 1,312 gigawatts of generation and 749 of storage. The wait is the striking number. “The median project built in 2025 took 61 months from the interconnection request to commercial operations, compared to 36 months in 2015 and 22 months in 2008.” Most projects never make it: only 13 percent of the capacity that asked to connect between 2000 and 2020 had reached operation by the end of 2025.
The same report separates the build from the wait. From a signed interconnection agreement to operation, the median project took 21 months in 2008 and 31 months in 2025. From the request to operation, it took 22 months in 2008 and 61 in 2025. Those medians cannot be subtracted from each other, but the shape is plain: most of the growth is in the time before anyone can build, not in the building.
Great Britain tells the same story with a different ending. By October 2024 the grid connection queue had “grown tenfold” in five years to 739 gigawatts, and the government and the regulator had already described “some customers being offered connection dates in the late 2030s.” Reform followed: by December 2025, Ofgem reported that the queue “has now been reduced by nearly two thirds.” The pressure has moved to demand. In July 2026 the regulator said demand connection applications had “surged from 41 gigawatts (GW) to 125GW, in under a year”, driven largely by data centres, “accounting for at least 80GWs.” Its review of the connection process recorded individual project delays “from six months to four years”, losses “from £600,000 to £36.5 million”, and costs rising “between 50% - 200% from the original quote to the final incurred bill.”
Globally, the International Energy Agency counted “at least 3 000 gigawatts (GW) of renewable power projects” waiting in grid connection queues in 2023, from countries holding about half of the world's wind and solar capacity. It added the sentence that frames this whole post: “New grid infrastructure often takes five to 15 years to plan, permit and complete, compared with one to five years for new renewables projects.”
The factory. A connection is useless without the equipment that makes it work, and the biggest pieces are made to order. The IEA's 2025 survey of industry found that it “now takes two to three years to procure cables and up to four years to secure large power transformers”, and that lead times for both “have almost doubled since 2021.” In the United States, the National Infrastructure Advisory Council put transformer lead times at “around 50 weeks in 2021” and “120 weeks on average in 2024”, with large units ranging “from 80 to 210 weeks”, and noted that “transformer prices are 80 percent higher since the beginning of the pandemic.” Wood Mackenzie's figures for the second quarter of 2025 showed a slight easing, to an average of 128 weeks for power transformers, 143 weeks for generator step-up transformers and 44 weeks for switchgear, against a forecast US supply shortfall of 30 percent for power transformers that year.
Gas turbines, which many data centre developers now want for on-site power, have their own queue. GE Vernova reported in October 2026 that its gas power backlog and slot reservation agreements had grown from 116 to 122 gigawatts, against annual output it plans to raise from 20 gigawatts in 2026 to 24 in 2028 and 30 in 2030. Slot reservations are not firm orders, so the backlog overstates certain demand, but the direction is clear. The IEA notes that “turbine deliveries for new gas-fired power plants now face lead times of several years.”
The permit office. For transmission, the IEA is blunt: “Permitting remains the primary cause of delays in transmission projects, particularly in advanced economies.” The picture is not static. In the United States, the Council on Environmental Quality found an average of 4.5 years to complete a federal environmental impact statement for those finished between 2010 and 2018, and a median of 2.2 years from notice of intent to final statement for those finished in 2024, measured differently but pointing the right way. In the European Union, the revised renewables directive caps permitting inside designated acceleration areas at twelve months, and two years for offshore projects. Permits are getting faster in places. They are still a queue the project does not control.
| Outside the fence | The evidence | Source |
|---|---|---|
| Grid connection, US | Median 61 months from request to operation for projects built in 2025; 22 months in 2008 | Lawrence Berkeley National Laboratory, Queued Up (2026) |
| Grid connection, Great Britain | Queue of 739 GW in 2024, cut by nearly two thirds by reform; data centre demand applications of at least 80 GW in 2026 | DESNZ (2024); Ofgem (2025, 2026) |
| Grid connection, data centre markets | Average wait in primary markets “exceeds four years” | JLL, Global Data Center Outlook (2026) |
| Large power transformers | Up to four years; lead times almost doubled since 2021 | IEA, Building the Future Transmission Grid (2025) |
| Power transformers and switchgear, US | 128 and 44 weeks on average, Q2 2025 | Wood Mackenzie (2025) |
| Gas turbines | Backlog and slot reservations of 122 GW against 20 GW a year of output | GE Vernova filings (2026) |
| Transmission permits | “The primary cause of delays”, particularly in advanced economies | IEA (2025) |
None of this means equipment and permits are the main cause of delay on every construction project. They are not: in the Associated General Contractors' 2026 survey, labour shortages were the most cited cause of delay, at 42 percent of firms, ahead of electrical equipment lead times at 29 percent and government delays at 26. The argument here is about a particular and fast-growing class of project, the ones whose value depends on being connected to something: power, a grid, a market. For them, the long pole has moved.
Data centres are the sharpest case
Data centres are the clearest example because the numbers are so large and the construction is so fast. The IEA estimates that data centres used about 415 terawatt-hours of electricity in 2024, around 1.5 percent of the world's consumption, and its 2026 update expects consumption to roughly double from 485 terawatt-hours in 2025 to 950 in 2030. The largest technology companies' capital expenditure “exceeded USD 400 billion in 2025 – and is expected to jump by another 75% in 2026”; Meta alone guided to $135–145 billion for 2026.
The building is not the slow part. JLL's 2026 outlook gives the comparison in two sentences, a few pages apart. “The average build time globally for a 50 MW data center is 18 months.” And “the average wait time for a grid connection in primary data center markets exceeds four years.” The same report says power, “not location or cost”, will be the primary site selection criterion because of “multiyear wait times for a grid connection.”
- On site
- Outside the fence
The longest waits are outside the fence. Weeks are converted to months for the scale.
JLL, 2026 Global Data Center Outlook (build time, grid wait); Wood Mackenzie, Oct 2025 (lead times); Lawrence Berkeley National Laboratory, Queued Up 2026 (interconnection).
| What | Time | Months on the chart | Where |
|---|---|---|---|
| Build a 50 MW data centre (global average) | 18 months | 18 | On site |
| Switchgear, US average lead time (Q2 2025) | 44 weeks | 10.2 | Outside the fence |
| Power transformer, US average lead time (Q2 2025) | 128 weeks | 29.5 | Outside the fence |
| Generator step-up transformer, US average (Q2 2025) | 143 weeks | 33 | Outside the fence |
| Grid connection, primary data centre markets (average) | more than 4 years | 48 | Outside the fence |
| US grid connection, request to operation (median project built in 2025) | 61 months | 61 | Outside the fence |
The pattern repeats in market after market. In Ireland, the energy regulator reports that data centres went from 5 percent of national electricity demand in 2015 to 22 percent in 2024, with a forecast of 31 percent by 2034, and new connections now come with conditions on where they may connect and how they are powered. In West London, a Greater London Authority paper described data centres along the M4 corridor creating “significant constraints on available electricity capacity”, and noted that “many developments (housing or otherwise) are receiving connection quotes into the 2030s.” The IEA estimates that, unless these grid risks are addressed, “around 20% of planned data centre projects could be at risk of delays.”
Developers have responded by going around the queue, with batteries and on-site generation, and by ordering early: JLL reports developers “preordering select materials as much as 24 months in advance to avoid project delays.” Even so, it found that 57 percent of data centre projects “experienced a construction delay of three months or more in 2025.” And the IEA cautions that, given the gas turbine supply crunch, “it is not clear that onsite generation necessarily promises a faster route to market for data centres at scale.” Going around one queue tends to lead into another.
Inside the fence, data centres are hard too, and it is worth being honest about that. HKA's 2026 analysis of projects that ended in claims found data centre extension-of-time claims averaging 112 percent of planned schedules, and costs claimed at 20.6 percent of budgets. The causes it names are design and integration: incomplete and inaccurate designs, dense building services, critical systems that have to work together. Those figures describe disputed projects, not data centres in general, and they are a reminder that the external critical path does not replace the internal one. It sits on top of it.
There is one more lesson in the research on modular projects. Flyvbjerg and colleagues' 2026 work on what they call modular natives shows solar power, electricity transmission and wind power as the three project types with the lowest cost overruns once built, and suggests data centres may belong in the same family. But their figures start at the final investment decision. The wait for a connection, an equipment slot or a permit mostly happens before that decision, outside those numbers. That is our reading rather than theirs, and it points the same way as everything else here: the projects that build best have their time risk before the build, in the queue.
Why the usual tools do not see it
A schedule built for site work treats the outside world as a set of dates. The grid connection is a milestone with a date typed in from the utility's offer letter. The transformer is a delivery milestone, often a constraint, sometimes a single line with a duration copied from the purchase order. The permit is a start-no-earlier-than date on the first activity that needs it. Each looks tidy on the Gantt chart. None behaves like the thing it represents. Three things go wrong.
The external date has no logic behind it. A milestone typed in from a letter cannot move by itself when the reality behind it moves. It moves when someone reads the next letter, understands it and retypes the date, which on a monthly cycle may be weeks later. Until then, the schedule reports a critical path that no longer exists.
The external date has no uncertainty. A site activity carries a range in any decent risk analysis. The connection date and the factory slot usually carry none, because nobody on the project knows how to estimate them, so they enter the simulation as certainties. The result is a risk analysis that measures the uncertainty in the part of the project the team controls and assumes away the part it does not.
The external date has no progress. On site, progress is measured every week. A transformer in a factory queue, a utility study in its third phase or an application on a planner's desk reports nothing between the order and the outcome. Controls sees the start and the promised finish and nothing in between. The first sign of a slip is often the slip itself.
The consequence is a familiar scene in a new setting. The site team works hard to recover two weeks on fit-out, the dashboard shows the recovery, and the project finishes on exactly the same day as before, because the date was never on site. Acceleration on a path with float buys nothing but cost.
A milestone with no logic, no range and no progress is not a plan. It is a promise somebody else made.
The new critical path
Take, for example, a data centre that can be built in the eighteen months JLL reports as typical, on a site where the utility offers a connection in four years, and where the main transformers have a lead time of around two and a half years from order. Build the halls as fast as possible and they sit finished and dark for more than two years. Start them later and the project ties up less capital, but now a slip in the connection or the transformer meets a site that has no slack left to absorb it. Either way, the critical path runs through the utility and the factory. The site is the float.
That inversion changes what a controls team is for. On a site-driven project, controls protects the date by managing the site. On an externally driven project, controls protects the date by knowing, earlier than anyone else, when the outside world moves, and by having the alternatives ready: a temporary connection, staged energisation of the first hall, a different supplier, a resequenced fit-out.
- Grid connection, 132 kVEnergised Q3 2028Utility · Connection offer, rev 2On track
- Main transformer T1Delivery week 50Supplier · Supplier letter: factory test movedSlipped 16 weeks
- Backup generatorsDelivery week 22Supplier · Order acknowledgedOn track
- Building permit, phase 2Decision MarchAuthority · Application lodgedWaiting
Critical path now runs through T1. Energisation moves 11 weeks unless resequenced.
Notice what made that sequence work. The supplier's letter was read the day it arrived and linked to the item it affected. The schedule knew the transformer was an activity with successors, not a date, so the effect on energisation was computed, not guessed: sixteen weeks of slip, five of them absorbed by float, eleven passed on. And a recovery option was tried as a copy of the plan before anyone committed to it. None of that is exotic. It is ordinary critical path discipline, applied to the part of the project that most schedules treat as weather.
What changes in the schedule
- Chains, not milestones. Model each external dependency as a chain of activities. For a large transformer: order, design approval, factory slot, manufacture, factory acceptance test, shipping, delivery, installation, testing. For a grid connection: the utility's study phases, the offer, the connection works, energisation. For a permit: application, consultation, decision, discharge of conditions.
- Owners and sources. Give each link an owner outside the project and a source for its date: the supplier's production schedule, the utility's offer letter, the authority's published timetable. A date without a source is a guess, and should say so.
- Ranges. Give each link a range, from the history of similar items where it exists, and run it through the risk analysis like any site activity. Then compare the spread of finish dates with and without the external ranges. The difference is the risk the old schedule was hiding.
- Progress outside the fence. Track the external equivalent of percent complete: drawings approved, core built, test passed, ship sailed; study phase complete, consultation closed. Ask for it, contractually if necessary.
- Plan the building to the power. If capacity arrives in steps, commission in steps. The earliest useful date is when the first block of capacity can be energised and used, not when the whole site is finished.
- A weekly external look-ahead. Keep a short list of the external items on or near the critical path and review it every week, with the same seriousness as the site look-ahead.
What changes in the contract
External dependencies are risk allocation problems as much as scheduling problems. Who carries the grid connection date: the owner who applied for it, or the contractor who must be ready for it? Who carries a transformer slip when the owner bought the transformer to secure a factory slot and the contractor must install it? Who carries a permit condition that arrives late and changes the work? The schedule is where these questions become visible. The contract is where they are answered.
- Name the external dependencies in the programme. Write them into the programme the contract requires, with their owners named, so that the accepted programme shows who is waiting for whom.
- Treat an external change as an event with a clock. Under most standard forms, the right to time and money depends on telling the other side promptly. A slipped factory test discovered in a supplier's letter is exactly the kind of fact that needs a notice decision within days, not at month end.
- Keep the evidence. When the dispute comes, the question will be what was known, when, and who was told. A record that holds the supplier's letter, the date it arrived and the scenario that showed its effect answers that question. A retyped milestone does not.
What changes in the team
A controls team built for site work reads site reports. A controls team for this class of project also reads supplier production schedules, factory test reports, utility study letters and permit portals, and understands what each one means for the date. That is a different skill set, closer to expediting and procurement than to traditional planning, and on most projects it sits in a different department with a different system.
The shift is to make external dependency control a controls discipline. The planner owns the external chains in the schedule. The procurement, grid and permitting teams own the facts that feed them. The two meet every week on one record, rather than in two spreadsheets that agree on a good day. For owners building many sites with the same equipment from the same suppliers, the same discipline scales up: one slip at one factory can touch several projects at once, and the portfolio needs to know that the day it happens.
Where AI helps, and where it does not
This is a problem made for machines that read, because the facts arrive as documents: letters, notices, revised offers, test reports, portal updates. The useful roles are specific.
- Reading what arrives. Extracting the dates from supplier letters, delivery notices, utility correspondence and permit updates, and linking each to the external activity it affects, with the source attached.
- Noticing change the day it happens. A factory test moved by sixteen weeks is visible when the letter lands, and the effect on the critical path is computed by the schedule engine, not estimated in a sentence.
- Trying the alternatives. Temporary connections, staged energisation, an alternative supplier, a resequenced fit-out, each tried as a scenario against the whole schedule, with its spread of outcomes rather than a single date.
- Seeing across a portfolio. Reading every letter across every site, so that a slip at one supplier shows up on every project it touches.
What AI does not change is who decides the external date. A machine can make a project know sooner and decide faster. It cannot make the factory build faster or the utility study shorter, and it should not be allowed to move a contractual date or send a notice on its own. The decision, and the name on it, stay with people.
Where it goes wrong
False precision. A date typed to the day from a letter that said “third quarter”. The schedule looks certain and the risk analysis believes it. Record the date as the source states it, with its range.
Buffering everything. A fixed contingency on every external link, until the plan is too long to approve and the buffers are quietly removed. The answer is ranges and a simulation that shows where the risk concentrates, not a pad on each line.
Constraints instead of logic. Pinning the energisation date so the schedule meets it. A hard constraint hides the slip it should reveal; schedule quality checks count hard constraints for exactly this reason.
One supplier, no fallback. A single factory slot with no alternative that anyone has tested. The time to find out what a second source would cost and take is before the first one slips.
Ignoring partial power. Planning for the whole site's capacity when the first block would let the first hall operate. Staging is often the largest recovery available, and it has to be designed in early.
Two records. Procurement's tracker says one date, the schedule says another, and nobody knows which is right. Every external date should live in one place, with its source, and every other view should read from it.
What changes for each person
The project director promises a date only after the external chains have ranges, and reports the external look-ahead to the board alongside the site progress. The big decisions move earlier: whether to stage energisation, whether to pay for a temporary connection, whether to secure a second source.
The planner owns the external chains as well as the site network, models supplier progress as progress, and runs the scenario the day an external date moves. A planner who can say within hours what a sixteen-week factory slip does to energisation, and what the three best responses are, is worth more on this class of project than one who can rebuild a site schedule overnight.
The procurement and expediting lead becomes a source of schedule facts. Production schedules, test dates and shipping become entries in the record rather than lines in a tracker, and the question they are asked changes from “what is the date?” to “what is the range, and what would move it?”
The grid or energy lead treats the utility relationship as a schedule input. Study phases and revised offers are tracked as activities, and the earliest useful date, the first block of capacity the site could actually use, becomes something to negotiate rather than accept.
The contract manager makes notice decisions on external changes within days, makes sure contracts allocate external risks explicitly, and keeps the evidence of when each fact was known.
The cost engineer prices waiting: finished capacity standing idle, extended site overheads, storage and insurance of equipment delivered early, financing during the wait. Set against the price of the alternatives, a temporary connection or a second supplier, that number is what turns a scheduling problem into a decision the director can make.
What to do on Monday
- List every external dependency on or near the critical path, with its owner outside the project and the source of its current date.
- Replace each external milestone with a chain of at least three links you can track.
- Put a range on each external link and run the risk analysis again. Compare the tail with and without the external ranges.
- Ask each critical supplier for a production schedule and a monthly update against it, and make it a requirement on the next order.
- Find the earliest useful date: the first block of capacity that could be energised, and what it would take to plan the site to it.
- Agree who decides on a notice when an external date moves, and how fast.
Where this stands
Verian is a project controls service run on Verian's own AI platform. Today, Verian's team keeps a client's schedule, cost, risk and contract record current every day. The platform reads connected mailboxes and channels and proposes risks from what arrives into a queue that a person validates, links documents to the activities they affect, tries recovery options as scenarios against the whole schedule, runs the risk analysis with a full critical path calculation in every iteration, and drafts notices against the contract's deadlines. The client's people see everything live and make the decisions.
The direction is the one this post describes: external dependency chains as a standard part of every schedule we keep, supplier, utility and permit facts read into the record the day they arrive, and a view across a client's portfolio for the items that many sites share. The rule underneath does not change. The machine reads and computes; a person decides, with a name and a time.
Much of this connects to what the evidence says about the projects that deliver: they think slowly before they commit and act fast once they do. Our report The 0.5% gathers that evidence in eleven pages, with every figure cited. Leave your work email below and we will send it to you.