Two years from now, in a hearing room, someone will ask one question about a day on your project: where is the record? Whatever was written down that day is what you will have to show them. We made a short film that follows one claim from the event to the decision, the way it should be run. This is the long read behind it, with every clause and every source.
The short version: a claim is not written at the end of a project. It is built on the day the event happens, by people who note what they see, and it runs on clocks the contract sets. AI changes how much of the project can be read and linked, and how fast a claim can be drafted. It does not change what the claim stands on. And it works for the other side too.
A claim is decided on the day it happens
FIDIC 2017 defines Contemporary Records as “records that are prepared or generated at the same time, or immediately after, the event or circumstance giving rise to the Claim.” The courts have read the same idea into earlier editions: in Attorney General for the Falkland Islands v Gordon Forbes Construction, contemporary records were original documents produced at or about the time of the claim, and witness statements written long after did not count. The Society of Construction Law's Delay and Disruption Protocol puts it plainly: records “must be generated contemporaneously as the works progress, and not afterwards,” and in a way that lets each one be matched to the activities in the programme.
The reason is simple. A record written after a dispute starts is evidence of an argument, not of the event. In Walter Lilly v Mackay, the experts agreed there was no programme of the outstanding works at the relevant date that could sensibly be used as a baseline, so a conventional delay analysis was not possible. Everything after that was harder and more expensive than it needed to be.
The stakes are large. In Arcadis's 2026 survey of construction disputes in the United States, the average dispute was worth US$56.0 million and lasted 12.2 months. The most common cause was a party “failing to understand and/or comply with its contractual obligations.” In Arcadis's last global edition, in 2022, the most common cause was “poorly drafted or incomplete and unsubstantiated claims.” HKA's CRUX dataset of 1,801 projects in 106 countries counted more than US$91 billion in dispute, with claimed costs averaging a third of committed capital expenditure, and contract management or administration failure as a cause on one project in five. None of these causes is exotic. They are the ordinary work of running a contract, not done on time.
The clocks
Every claim runs on clocks that the contract sets, and most of them start before anyone writes a word. Here are the ones that matter for one claim under the two forms most of our readers work with.
| Step | FIDIC 2017 | NEC4 ECC |
|---|---|---|
| Notify the event | 20.2.1: as soon as practicable, and no later than 28 days after you became aware, or should have become aware | 61.3: within eight weeks of becoming aware that the event has happened |
| If you miss it | No additional payment, no extension of time, the other Party discharged (subject to 20.2.5) | Prices, Completion Date and Key Dates not changed, unless the event arose from the Project Manager's own instruction, notification, certificate or changed decision |
| The other side's silence | 20.2.2: if the Engineer does not say within 14 days that the Notice was late, it is deemed valid | 61.4: one week to reply; if you remind and the silence lasts two more weeks, the event is accepted |
| The detailed submission | 20.2.4: fully detailed Claim within 84 days of awareness | 62.3: quotation within three weeks of the instruction; reply within two |
| The decision | 3.7.3: 42 days to agree, then 42 more to determine; no notice means the Claim is deemed rejected | 62.6: silence on a quotation, a reminder and two more weeks: accepted |
| If you disagree | 3.7.5: 28 days to give a Notice of Dissatisfaction, then the DAAB | Adjudication under the dispute resolution option chosen |
Four details on these clocks are worth knowing well.
Notify on the event, not on the delay. The courts do not agree on when the FIDIC clock starts. Both leading cases were decided on the 1999 wording, which the 2017 books carry forward. In Obrascon v Gibraltar (2014), the English Technology and Construction Court read the clause broadly: notice need not be given until there actually is delay, though it can be given earlier. In Panther v Modern Executive Systems (2022), the Dubai International Financial Centre Court of Appeal disagreed: the 28 days run from awareness of the event or circumstance giving rise to the claim, not of the delay. The contractor in that case lost its extension of time for want of a valid notice. The rule that survives both readings is to notify when the event happens.
The 84-day lapse is narrower than people think. Under 20.2.4, what lapses the Notice of Claim is a missing statement of the contractual or legal basis, and only if the Engineer says so within 14 days. The rest of the fully detailed Claim can follow. The 2022 reprint of the 2017 books changed “shall include” to “shall be supplemented with”, and because the 84 days run from awareness, a notice given on day 28 leaves only 56 days to write the claim, a point FIDIC's own 2022 guidance makes for termination claims.
Silence has dates. FIDIC's clocks are two-sided. An Engineer who stays silent for 14 days has accepted a notice as valid; one who stays silent for 42 days and then 42 more has rejected the Claim, and your 28 days to say you are dissatisfied are running. Under NEC4, a Project Manager who stays silent for a week, and two more weeks after a reminder, has accepted the event. A clock register has to track these as dates, not reminders. CECA's 2025 bulletin on NEC deemed acceptances notes that many cloud contract systems do not apply them at all, so someone has to adjust the record by hand.
An NEC early warning does not stop the eight-week clock. CECA's Bulletin 13 says it directly: a contractor may think that by giving an early warning it can never be time-barred, “but this is not correct.” There is a further trap. The duty to notify turns on the contractor's belief that an event is a compensation event, while the bar runs from awareness that the event happened. Belief can come later than awareness.
Step one: find the event
Events rarely announce themselves as claims. They sit in a line of the site diary, an item in the minutes (“Rock found in the cutting. Noted.”), an RFI response that changes a detail, a letter that grants access a week late. HKA's data shows where they come from most often: change in scope on 38.8% of projects, design information issued late on 22.5%, restricted or late access on 17.9%, unforeseen physical conditions on 17.8%.
FIDIC's test matters here: “aware, or should have become aware”. The second half is objective. A document that reached the project can start the clock even if nobody read it. That is the strongest case for AI in claims: reading every incoming letter, minute, diary entry and email as it arrives, and flagging the passages that may be notice events, with the clause that might apply and the date awareness began.
The evidence on how well AI does this is still early. On narrow, labelled tasks, clause classification works: a 2022 study in Automation in Construction trained a BERT model on 2,807 clauses from 56 construction specifications and reached an F1 score of 0.934 across seven risk categories. But the common failure of language models on contracts is the missed clause: the ContractEval study of 19 models in 2025 found that open models often answer “no related clause” when one exists. For a time bar, the miss is the expensive error. We found no published study that measures how well AI detects notice events in construction correspondence. So treat your AI as a second reader that reads everything, never as the only reader, and have a person confirm each event and its awareness date.
Step two: start the clock, and give notice
Once a person confirms an event, the dates follow from the contract: notice by day 28, the fully detailed claim by day 84, interim updates monthly if the effect continues. This is arithmetic on the contract's own periods and its calendar, and it should be done by a tool, not estimated by a model. A time bar is binary. “About a month” is not a date.
The notice itself has a form. Under FIDIC 2017, Sub-Clause 1.3, a Notice is in writing, signed by an authorised person (or an electronic original where the Contract Data allows), identified as a Notice and delivered to the Engineer. Fenwick Elliott's commentary adds that nothing in a progress report or a programme counts as a Notice. Your AI can draft it; a person with authority decides to send it and signs it. The clocks apply to the Employer's claims too: under 20.2.1, an Employer who misses the 28 days cannot reduce the Contract Price.
Step three: keep the records while the work runs
From the event onward, the records clip onto it every day. Sub-Clause 20.2.3 lets the Engineer monitor them, instruct further records and inspect them, without admitting their accuracy. The SCL Protocol's first core principle is that the parties should agree at the start what records will be kept, and resource it. It lists six kinds: programme, progress, resource, cost, correspondence and administration, and contract and tender documents. Progress, resource and cost records should set out facts only, offer no opinions, and where practical be signed by both sides. Emails, programmes and spreadsheets with formulae should be kept in their native format.
This is the second place AI earns its keep. Each diary entry, plant return, photo and survey can be linked, as it arrives, to the event and to the programme activity it evidences. The SCL test that a record must be matchable to the programme is almost impossible to meet two years later. It is routine on the day.
Step four: measure the time
The method most contracts expect while the work is running is a prospective time impact analysis. The SCL Protocol (4.8) sets out the steps: bring the programme fully up to date to the point immediately before the event, with every delay to that date, the contractor's included; add any reasonable recovery plans; insert a fragnet, the small network of new activities the event requires, linked into the programme; and read the effect on completion. NEC4's clause 63.5 does the same by contract, from the Accepted Programme current at the dividing date.
Say the excavator hits rock where the ground report showed clay. The fragnet might be three activities: break out the rock, remove the extra spoil, re-survey. Inserted after the excavation it interrupts, it pushes drainage, sub-base and pavement, and completion moves, say, 23 days. That is the extension sought: from the logic, not from a feeling. Had the rock hit work with enough float, the date might not have moved at all. The Protocol's Core Principle 8 is that unless the contract says otherwise, float belongs to the project, and an extension is due only to the extent the delay takes total float on the critical path below zero. NEC4 differs: because it measures the movement of planned Completion, terminal float is generally read as staying with the contractor.
| Method | Critical path from | Delay impact | When it fits |
|---|---|---|---|
| Impacted as-planned | the plan | forecast | Early, simple, with a sound plan |
| Time impact analysis | updates at the time | forecast | During the works, event by event |
| Time slice windows | updates at the time | measured after | Good updates throughout |
| As-planned v as-built windows | updates at the time | measured after | A plan and as-built records |
| Longest path, looking back | the as-built | measured after | As-built data, after the fact |
| Collapsed as-built | the as-built | measured after | Strong as-built records |
Three cautions from the standards. AACE's RP 29R-03 is blunt: “All methods are subject to manipulation as they all involve judgment calls by the analyst,” and schedules “do not demonstrate root causation or responsibility for delays.” Its RP 52R-06 adds that a prospective analysis loses validity as time passes between the event and its approval. And the SCL Protocol warns that “simply stating that Employer Risk Events have occurred and claiming the whole of any delay apparent at the time of the events is not a proper demonstration of entitlement.” Since the 2022 reprint, FIDIC's Sub-Clause 8.5 also says the Engineer “may increase, but shall not decrease, the total EOT,” which rewards getting the first assessment right.
The division of labour here is clear. AI can draft the fragnet from the event's records: the activities, the durations, the ties. The critical path is computed by the scheduling engine, in the same software as the accepted programme. A planner reviews the logic, and a person approves the measurement.
Concurrency: when your own delay sits on the same path
Now suppose your own site diary says the crane was down for six days, waiting for a hydraulic part, in the same fortnight, on the same path. That is a candidate for concurrent delay: two delays at the same time, one the employer's risk and one yours, both affecting completion. The SCL Protocol's answer comes in two parts. Core Principle 10: the contractor's concurrent delay “should not reduce any EOT due.” Core Principle 14: the contractor recovers compensation only “if it is able to separate the additional costs caused by the Employer Delay from those caused by the Contractor Delay.” Time, yes. Money, only for what you can separate.
English law has taken the same line on time since Henry Boot v Malmaison (1999); in Walter Lilly the court held that a contractor is entitled to a full extension where one of two effective causes is a relevant event, and that the Scottish apportionment approach does not apply. But the parties can contract out of it: in North Midland Building v Cyden Homes (2018), the Court of Appeal upheld a bespoke clause saying concurrent delay would not count towards an extension. FIDIC 2017 leaves the rule to the contract: concurrent delay is assessed under the Special Provisions, or if none are stated, “taking due regard of all relevant circumstances.” The Protocol also notes that true concurrency is rare, and that a later employer delay sitting inside an existing contractor overrun is not concurrent at all on its view.
Step five: price the money
Money is built from the same records, line by line: plant hours at their rates, the crew's standing time, the extra spoil hauled, the site's running costs for the period. Not a percentage of the contract sum.
The clause decides what can be recovered. FIDIC 2017 defines Cost as expenditure reasonably incurred, including overheads, “but does not include profit”; Cost Plus Profit adds the percentage in the Contract Data, five percent if none is stated. HKA's table of the 2017 Red Book shows the pattern. Unforeseeable physical conditions (4.12) give time and Cost, but no profit. Delays caused by authorities (8.6) give time only. Late access to site (2.1), late drawings or instructions (1.9) and a long list of other employer-risk events give Cost Plus Profit.
Three more rules shape the figure. Prolongation is compensated at actual cost, not tender rates (SCL Core Principle 20), and it is priced in the period when the effect was felt, not by reference to the extended period at the end of the job (Core Principle 22): site overheads in month seven can be very different from the run-out month. An extension of time does not automatically bring money, nor money an extension (Core Principle 12). And disruption, lost productivity, is best shown by a measured mile: impacted against unimpacted periods of the same work. The Protocol calls it “the most widely accepted method,” and warns that every adjustment makes it “more theoretical and unreliable.” AACE's RP 25R-03 explains why production is not productivity: a crew can lay its planned 300 feet of pipe a day and still spend twice the planned labour, “100% of planned production but operating at 50% productivity.”
Global claims are the end point of missing records. The SCL Protocol discourages them, and warns that a global claim “will fail entirely if any material part of the global loss can be shown to have been caused by a factor or factors for which the Employer bears no responsibility.” Walter Lilly allowed that a global claim is not wrong in principle, but required the contractor to show its loss would not have been incurred anyway, including that its tender was priced well enough to have made a return.
Step six: the fully detailed claim
By day 84 under FIDIC, the fully detailed Claim: a description of the event, the statement of the contractual or legal basis, the contemporary records relied on, and the detailed calculations of time and money. Where the effect continues, 20.2.6 makes the first submission an interim claim, followed by monthly updates and a final claim within 28 days after the effects end. Meanwhile, 20.2.7 lets amounts reasonably substantiated be included in payment certificates.
This is where AI saves the most hours, and where it carries the most risk. Your AI can draft the narrative quickly from the linked records. The rule that keeps it safe is simple: every sentence that states a fact, a date or a figure carries a pin to the record it comes from, and someone opens every pin before the claim goes out. No record, no sentence.
No record, no sentence.
Step seven: after you submit
Under FIDIC 2017 the Engineer has 42 days to reach agreement and, failing that, 42 more to determine; the determination must also decide whether the notice was valid. A party that disagrees has 28 days to give a Notice of Dissatisfaction, and must then refer the dispute to the Dispute Avoidance/Adjudication Board within 42 days. The board decides within 84 days, and its decision binds the parties at once, “whether or not a Party gives a NOD.” Another 28 days to give a Notice of Dissatisfaction with the decision, 28 days for amicable settlement, and then ICC arbitration. On the contract's own maximum periods, that is about a year from the event to the start of arbitration, before anyone extends anything.
The other side has AI too
The Engineer's team, the employer's claims consultant and eventually the tribunal's experts can now read your whole record in minutes, not just the parts you sent. That cuts both ways. If your diary says the crane was down, their AI will find it. If your claim says the crew stood down again on day 12, they will open the reference. If there is no such entry, your credibility goes with it.
The courts have already seen what happens when AI-drafted text is not checked. In Mata v Avianca (New York, 2023), lawyers filed six non-existent judicial opinions created by ChatGPT, and were fined US$5,000. When the lawyer asked the tool whether a case was real, it said the case “does indeed exist.” Asking the same model to check itself is not checking; opening the source is. In Ayinde v Haringey and Al-Haroun v Qatar National Bank (London, 2025), the Divisional Court found that in one schedule of 45 citations, 18 cases did not exist, and warned that freely available generative AI tools “are not capable of conducting reliable legal research.” A public database kept by Damien Charlotin listed 2,302 court decisions involving AI-invented content on 16 November 2026. And the tools built for lawyers are not immune: a Stanford study found leading legal research AI tools hallucinated between 17% and 33% of the time.
Arbitral institutions are writing rules. The Chartered Institute of Arbitrators' 2025 guideline lets a tribunal require disclosure of AI use where it may affect the evidence or the outcome, and says the use of AI does not diminish anyone's responsibility. The Silicon Valley Arbitration and Mediation Center's guidelines deem parties “responsible for any uncorrected errors or inaccuracies in any output produced by an AI tool they use,” and say confidential information should not go into any AI tool without vetting and authorisation. The practical consequence: keep a log of the tool, the version, the prompt and the output for anything AI drafted in a claim, because a tribunal may ask for it.
Who does what
| Task | Who does it | Why |
|---|---|---|
| Read every letter, minute, diary entry and email; flag candidate notice events with the passage and a proposed clause | AI proposes; a person confirms | “Should have become aware” makes unread documents a live risk |
| Compute every deadline, and the other side's silences | A deterministic tool, never a model | A time bar is binary |
| Decide to notify; sign and issue the notice | A person with authority | FIDIC 1.3: signed, identified as a Notice |
| Link each record to the event and the programme activity | AI proposes links; a person accepts | SCL 1.7: records matchable to the programme |
| Draft the fragnet | AI drafts; the planner reviews | SCL 4.10: in the same software as the programme |
| Compute the effect on completion | The scheduling engine (CPM) | The impact is a calculation, not a narrative |
| Price time and cost from the records | Calculations from cost records; a person checks | SCL Core Principles 20 and 22 |
| Draft the claim, every sentence pinned to a record | AI drafts; a person opens every pin | <em>Mata</em>, <em>Ayinde</em> |
| Agree the analysis method with the other side | People | SCL 11.8 |
| Determine, adjudicate, award | The Engineer, the board, the tribunal | CIArb 2025: decisions are not delegated to AI |
How it goes wrong
- The notice is given when the delay shows, not when the event happened, and the 28 days or eight weeks have already run.
- An NEC early warning is taken for a notice of a compensation event.
- The event is mentioned in a progress report or the minutes, and nobody issues a Notice in the contract's form.
- Records are rebuilt at the end of the job, and cannot be matched to the programme.
- The fragnet goes into a programme that is months out of date, or leaves out the contractor's own delays to that point.
- The extension is claimed on work that had float.
- Prolongation is priced at the run-out month rather than when the effect was felt.
- A global claim carries one cost driver the employer is not responsible for, such as a thin bid, and fails whole.
- An AI-drafted sentence cites a record nobody opened, or the model is asked to check its own work.
- A confidential bundle is pasted into a public AI tool.
What to do on Monday
- Build the clock register for every live contract: each notice period and each of the other side's silences, as dates, computed from the contract and its particular conditions.
- Point your AI at the incoming flow (letters, minutes, RFI responses, diaries, email) and have it flag candidate events with the passage and a proposed clause. A person confirms each one, and the awareness date, the same day.
- Agree at the start what records will be kept, and link each one to the event and the programme activity as it arrives.
- Keep the programme updated, so a fragnet can always go into the update just before the event.
- Adopt the rule for anything AI drafts: no record, no sentence. Open every pin before a claim goes out, and log the tool, version, prompt and output.
- Assume the other side will read your whole record. Look for your own delays on the same path before they do.
Where Verian fits
This is how we run claims at Verian. The notice clocks come from the contract's own confirmed clauses or a verified rule library for the form, and are computed, never estimated by a model; the awareness date is always a person's statement. The delay is measured by re-running the programme's critical path, with the method chosen by rule, and a person approves the measurement. Every sentence in the case file cites a record and is checked against that record's stored text, and the approved file is frozen into a fingerprinted PDF with an exhibit index.