Project controls glossary
The working vocabulary of project controls on capital projects: 85 terms from the schedule, the cost, the risks, the contract and the changes, each in one or two plain sentences.
The discipline
- Project controls
- The discipline that keeps a capital project on time and on budget: planning and scheduling, cost control and forecasting, risk management, contract administration and change control.
- Capital project
- A large, long-lived investment in a physical asset such as a plant, a terminal, a rail line or a power station, built once, over years, under contract.
- Owner
- The organisation that pays for the asset and will run it, also called the owner-operator. It sets the budget and the dates and carries the consequences when they are missed.
- EPC contractor
- A contractor that takes on the engineering, the procurement and the construction of a project under one contract, often for a fixed price and date.
- Baseline
- The approved version of the schedule or the budget that progress is measured against. It changes only through a formal approval.
- Work breakdown structure (WBS)
- The project's scope set out as a tree of deliverables. The schedule and the cost are both organised on it, which is what lets them be compared.
- Progress measurement
- The rules by which work is counted as done: units installed, milestones reached or weighted steps. Earned value is only as good as these rules.
- Project record
- The single, current set of facts about a project: its schedule, cost, risks, contract and changes, each tied to the document it came from.
- Decision latency
- The time between a fact appearing on a project and a decision being taken on it. Where facts travel by monthly report, it is measured in weeks.
Schedule
- Activity
- A piece of work in the schedule with a duration, a start and a finish.
- Milestone
- A point in the schedule with no duration that marks an event: a contract date, a delivery, a handover.
- Logic link
- The dependency between two activities, also called a relationship. Finish-to-start is the most common: the second cannot start until the first has finished. A lag adds a fixed wait to the link.
- Critical path method (CPM)
- The calculation that turns activities, durations and links into dates. A forward pass gives the earliest dates, a backward pass gives the latest, and the gap between them is the float.
- Critical path
- The chain of linked activities that sets the project's finish date. A day lost on it is a day lost at the end unless it is recovered.
- Longest path
- The continuous chain of activities that runs from the data date to the last activity in the schedule. It is the critical path found by following the logic instead of a float threshold.
- Total float
- How long an activity can slip without moving the project's finish date or a constrained milestone.
- Free float
- How long an activity can slip without delaying the earliest start of any activity that follows it.
- Data date
- The date up to which progress has been recorded in the schedule. Everything before it is actual; everything after it is forecast.
- Constraint
- A date fixed on an activity by hand instead of by logic, such as a start no earlier than a given day. Too many constraints hide the real critical path.
- Calendar
- The working days and hours assigned to an activity or a resource, including holidays and shutdowns.
- Resource loading
- Assigning labour, equipment and materials to activities, so the schedule shows how many people and machines each week needs.
- Look-ahead
- A short-range plan, usually the next two to six weeks, taken from the schedule for the people doing the work.
- Basis of schedule
- The written record of what the schedule assumes: scope, sources, calendars, production rates, sequence, risks and exclusions.
- Schedule quality check
- A set of tests on how a schedule is built: missing links, long lags, hard constraints, very high float and others. The best known is the 14-point assessment of the US Defense Contract Management Agency (DCMA).
- Recovery schedule
- A revised plan that shows how lost time will be won back: more resources, a changed sequence or work done in parallel.
- Scenario
- A copy of the schedule in which a recovery or a what-if can be tried without touching the live plan or the baseline.
- XER
- The file format in which Oracle Primavera P6 exports a schedule. It is the usual way a schedule moves between companies and tools.
- 4D scheduling
- The schedule linked to the 3D model, so the build can be played in sequence over time and progress can be shown on the model. 4D Scheduling in Verian
- IFC
- Industry Foundation Classes, the open file format for building and infrastructure models (ISO 16739).
- Delay analysis
- The study of what delayed a project and who is responsible, usually to support or answer a claim. Common methods are time impact analysis and windows analysis.
- Time impact analysis
- A delay analysis method that inserts a delay event into the schedule as it stood just before the event and measures the effect on the completion date.
- Windows analysis
- A delay analysis method that divides the project into periods and, in each one, compares what was planned with what happened to find which events drove the critical delay.
- Concurrent delay
- Two delays, one at the owner's risk and one at the contractor's, acting on the completion date over the same period. Contracts and courts differ on how it is treated.
Cost
- Budget at completion (BAC)
- The total approved budget for the work.
- Commitment
- Money promised under a purchase order or a contract but not yet invoiced.
- Actual cost (AC)
- What the work done so far has cost.
- Planned value (PV)
- The budgeted cost of the work that was scheduled to be done by now.
- Earned value (EV)
- The budgeted cost of the work actually done by now.
- Earned value management (EVM)
- The method that compares planned value, earned value and actual cost to show, in one set of figures, whether a project is ahead or behind and over or under budget. Financial Controls in Verian
- Cost variance (CV)
- Earned value minus actual cost. A negative figure means the work done has cost more than budgeted.
- Schedule variance (SV)
- Earned value minus planned value. A negative figure means less work has been done than planned.
- Cost performance index (CPI)
- Earned value divided by actual cost. Below 1.0, each unit of money spent has bought less than a unit of budgeted work.
- Schedule performance index (SPI)
- Earned value divided by planned value. Below 1.0, less work has been done than the plan called for by this date.
- Estimate to complete (ETC)
- The forecast cost of the work still to be done.
- Estimate at completion (EAC)
- The forecast total cost at the end: actual cost to date plus the estimate to complete. One common formula is the budget at completion divided by the CPI.
- Variance at completion (VAC)
- Budget at completion minus estimate at completion: the forecast overrun or underrun.
- To-complete performance index (TCPI)
- The cost efficiency needed on the remaining work to finish on budget: the budgeted cost of the remaining work divided by the budget that is left.
- Contingency
- An amount inside the budget for identified risks and for uncertainty in the estimate. It is released by approval as risks happen or pass.
- Management reserve
- An amount held above the project budget, under senior management's control, for events nobody identified.
- Trend
- An early record of a likely change to cost or time, raised before the change is approved so the forecast can include it.
- S-curve
- A chart of cumulative cost or progress over time, named for its shape: slow, then fast, then slow. Plan and actual are drawn together to show the gap.
- Cash flow forecast
- Money in and money out by period, taken from the cost forecast and the payment terms.
- Cost breakdown structure (CBS)
- The budget set out as a tree of cost accounts, mapped to the work breakdown structure so cost and schedule can be compared.
- Basis of estimate
- The written record of how an estimate was built: scope, quantities, rates, sources, allowances and exclusions.
- Estimate class
- AACE International's five classes of estimate, from Class 5 (the least defined, at concept stage) to Class 1 (the most defined). The class indicates the accuracy range to expect. Cost Estimating in Verian
Risk
- Risk register
- The list of a project's risks, each with its cause, its likelihood, its effect on time and cost, its owner and its response.
- Risk response
- What is done about a risk: avoid it, reduce it, transfer it or accept it. A response has its own cost and its own owner.
- Three-point estimate
- An optimistic, a most likely and a pessimistic value for a duration or a cost, used as the range in a simulation.
- Monte Carlo simulation
- A calculation run thousands of times, each run drawing durations, costs and risk events at random from their ranges, to show the spread of possible outcomes instead of one date or one figure.
- Schedule risk analysis
- A Monte Carlo simulation of the project's own schedule, logic included, that gives the chance of meeting a date and names the activities and risks that drive the result. Also called quantitative schedule risk analysis (QSRA). Risk Management in Verian
- Cost risk analysis
- A Monte Carlo simulation of the estimate or the forecast that gives a range for the final cost and the contingency needed for a chosen level of confidence. Also called quantitative cost risk analysis (QCRA).
- Deterministic date
- The single finish date the schedule calculates with no uncertainty applied. A risk analysis shows how likely that date is.
- P50, P80, P90
- The date or cost that 50, 80 or 90 per cent of the simulated outcomes meet or beat. A P80 date is one the project finishes by in eight runs out of ten. A P80 is a date. The tail is the story.
- Tornado chart
- A ranked bar chart of the activities or risks that most influence the finish date or the cost in a simulation.
- Criticality index
- The share of simulation runs in which an activity sits on the critical path.
- Joint confidence level
- The probability of meeting the cost target and the date together, read from a simulation of both.
- Reference class forecasting
- Forecasting a project's cost and duration from the actual outcomes of similar past projects, to correct for the optimism in its own plan.
Contract and change
- Obligation
- Something a party must do under the contract, by a date or on an event: submit a programme, give a notice, provide access. Contract Intelligence in Verian
- Notice
- A formal written communication the contract requires within a set period, for example to warn of a delay or to start a claim.
- Time bar
- A contract deadline after which an entitlement that was not notified is lost.
- Extension of time (EOT)
- More time to complete, granted under the contract for a delay that is not at the contractor's risk. It moves the completion date and, with it, any delay damages.
- Delay damages
- A sum fixed in the contract that the contractor pays for each day or week of late completion. Also called liquidated damages.
- Variation
- An instructed change to the scope, the design or the way the work is done, valued under the contract. Also called a change order.
- Change control
- The process by which a proposed change is recorded, measured for its effect on time, cost, scope and risk, and approved or rejected by the people with authority. Change Control in Verian
- Claim
- A request for more time or money under the contract, supported by notices, records and analysis.
- FIDIC
- The International Federation of Consulting Engineers, and the standard forms of contract it publishes for international construction, among them the Red, Yellow and Silver Books.
- NEC4
- The fourth edition of the New Engineering Contract, a family of standard forms widely used in the United Kingdom, built around early warnings, an accepted programme and compensation events.
- Compensation event
- In NEC contracts, an event that is not at the contractor's risk and that changes the prices and the completion date when it happens, assessed by its effect on the programme.
- Early warning
- In NEC contracts, the duty of each party to tell the other as soon as it sees something that could affect cost, time or quality.
AI in project controls
- AI project controls
- Project controls in which software reads the project's own documents and systems, keeps one project record from them, answers questions from that record with computed figures and their sources, and proposes changes that people approve. What is AI project controls
- Agentic project controls
- Project controls in which AI agents do the gathering, the checking and the drafting across the schedule, cost, risks, contract and changes, and put each proposal in front of the person with the authority to approve it. What is agentic project controls
- AI agent
- Software built on a language model that carries a task through several steps, using tools and the permissions it has been given, and returns a result for review.
- Provenance
- The recorded source of a line or a figure: which document, which library, which tool.
- Human approval
- The rule that an AI's proposal changes nothing until a named person with authority accepts it. Also called human in the loop.
- Hallucination
- A fluent statement by a language model that its sources do not support. In project controls the guard is that figures are computed by tools from the record and never written by the model. Figures by tools, sentences by the model
Where these terms are used
Verian is an AI project controls platform for capital projects. Its agents work on the schedule, the cost, the risks, the contract and the changes on one project record, with every figure computed from that record and every change approved by a person. It is offered on its own or with Verian’s team running it.